Planning- Minutes of Meeting
CEB2003
Software Project Management
Instructor:
Pn Norlini Ramli
Anonymous
Meeting Minutes
MEETING MINUTES 1 (Planning)
Date: 25 June 2010
Time: 7.30 – 8.30 pm
Type/Location: MSN Messenger
Attendees | Fasasi, Suria, Haemashini, Jasimah |
Not Attending | - |
No | Agenda | Action By |
1 | Short briefing of the meeting - Briefing by project leader on the today’s agenda and the project progress. | Fasasi |
2 | Work Breakdown Structure - A work breakdown structure of the project was being discussed. - The task and responsibilities of each team members are identified for the Work Breakdown Structure | Haemashini and Jasimah |
3 | Start system development - The system is 50% already being developed - Login interface and databases of student information completed. | Fasasi and Suriavarman |
4 | Schedule next meeting. - Based on the progress made this week, next meeting is scheduled to continue through face to face meeting | All members |
Date: 5 July 2010
Time: 5.30 – 7.30 pm
Type/Location: Student Lounge
Attendees | Fasasi, Suria, Haemashini, Jasimah |
Not Attending | - |
No | Agenda | Action By |
1 | Meeting Briefing - Project leader briefed on the today’s agenda, project progress and corrections that need to be made for previous meeting | Fasasi |
2 | Work Breakdown Structure - The Microsoft Project is downloaded. - The a more detailed and completed Work Breakdown Structure is created by Haema and Jasimah | Haemashini and Jasimah |
3 | Start system development - System coding progress is around 75%, | Fasasi and Suriavarman |
4 | Schedule next meeting - The next meeting is scheduled on the 9thJuly to discuss the final product of the system as well as the documentation | All Members |
In : Project Planning