CEB2003

Software Project Management

 

Instructor:

Pn Norlini Ramli

 

 

Anonymous

Meeting Minutes

 

 

MEETING MINUTES 1 (Planning)

Date: 25 June 2010

Time: 7.30 – 8.30 pm

Type/Location: MSN Messenger

 

Attendees

Fasasi, Suria, Haemashini, Jasimah

Not Attending

-

 

No

Agenda

Action By

1

Short briefing of the meeting

-          Briefing by project leader on the today’s agenda and the project progress.

Fasasi

2

Work Breakdown Structure

-          A work breakdown structure of the project was being discussed.

-          The task and responsibilities of each team members are identified for the Work Breakdown Structure

Haemashini and Jasimah

3

Start system development

-          The system is 50% already being developed

-          Login interface and databases of student information completed.

Fasasi and Suriavarman

4

Schedule next meeting.

-           Based on the progress made this week, next meeting is scheduled to continue through face to face meeting

All members

 

 




 MEETING MINUTES 2 (Planning)


Date: 5 July 2010

Time: 5.30 – 7.30 pm

Type/Location: Student Lounge

 

Attendees

Fasasi, Suria, Haemashini, Jasimah

Not Attending

-

 

No

Agenda

Action By

1

Meeting Briefing

-          Project leader briefed on the today’s agenda, project progress and corrections that need to be made for previous meeting

Fasasi

2

Work Breakdown Structure

-          The Microsoft Project is downloaded.

-          The a more detailed and completed Work Breakdown Structure is created by Haema and Jasimah

Haemashini and Jasimah

3

Start system development

-          System coding progress is around 75%,

Fasasi and Suriavarman

4

Schedule next meeting

-          The next meeting is scheduled on the 9thJuly to discuss the final product of the system as well as the documentation

All Members